Pukekohe Electrification and Upgrades

Following the progress of rail upgrades and electrification between Papakura and Pukekohe
153 photos in this gallery. Showing photos 145 - 153

With track work now largely complete, attention has shifted to the platform and its fixtures. Shown here are the new shelters on the new platform, conveniently starting at the stairs

12 February 2024

The stairs themselves are also covered, and alongside the existing shelters, passengers can stay dry all the way from the bus to their train

12 February 2024

Working in the station area is ETM 622 and ETM 676, putting the final touches on the track

12 February 2024

ETM 622 and ETM 676 sit at the platform shortly before doing another run on the tracks. The track on the right appears to be a backshunt from the stabling yard, with trains not able to access the eastern platforms directly from there

12 February 2024

Looking north, the new platform and shelters are starting to look like a completed station again

12 February 2024

With the end of the upgrade project fast approaching, station signage has now started appearing around the platforms

26 April 2024

The bridge over the station has had its sides temporarily boarded up, while finishing touches are applied to the station

26 April 2024

The southern end of the new shelter on the existing platforms are almost complete, while the northern half still needs the surface sealed

26 April 2024

Hi-rail vehicles sit on the backshunt waiting for their next duties while other work is carried out

26 April 2024

Search
Sort
Licencing
Creative Commons License
All photos and videos on this site are licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.
Attribution to https://nzrailphotos.co.nz is required. If you wish to use photos for commercial use or for an exception to this licence, please seek permission first. Fees may apply.